How to change the direction of joist on a drawing that have been added using either Ring + Plate + Subfloor + Joist?

Version(s): 10, 11
The joists have been added to the drawing using the Joist Poly command. To change the direction, you need to change the edge which is being used as the Joist Reference edge. The Reference Edge is denoted by the double red XX. To change the edge where joist measure their spacing from, select Edit> Edit Item, followed by Misc > Locate Type > Joist, then select the edge desired to be the Referenced side. On the prompt, check the box to have the referenced side enabled.